Nebius plans $40 billion of spending for 2027 as Microsoft capacity slips to Q2 2027
Nebius told investors on its third-quarter call that it plans 40 billion dollars of spending in 2027, funded largely by customer prepayments and loans backed by customer contracts. It also cut its 2026 revenue forecast to 3 billion dollars.
Why it matters
Third-quarter revenue came in at 981 million dollars, up 571 percent from a year earlier, though roughly a third of that was a one-time payment tied to a new partnership model. Nebius guided 2027 revenue to 12 to 13 billion dollars. It expects to break even on a pre-tax basis by the fourth quarter.
The plan depends on capacity Nebius does not fully control. Only just over half of the Microsoft capacity tied to a Vineland, New Jersey site is now scheduled for delivery by the end of the year, with the rest moving to the second quarter of 2027. Chief executive Arkady Volozh said building at this scale is hard and that Nebius is not immune to delays.
Nebius says the data centres it builds itself are coming online on time or ahead of schedule, and that prepayments plus financing of investment-grade contracts should cover up to 85 percent of the 40 to 45 billion dollar capital spend. It ended the quarter with 7.4 billion dollars in cash. Shares ended the day down 17 percent.